VINFAST PROJECT

VINFAST . AUTO & ELECTRIC VEHICLE FACTORY
 
Requirements: solution design, supply and complete installation of all equipment for Vinfast electric motorcycle frame welding workshop according to European standards in terms of workspace, occupational safety and product quality
 
Number of robot welding stations: 21
 
Number of welding robots: 25 ABB . robots
 
Total installation time to complete: From March 2018 to September 2018
 
Result: Weldcom completed the project on time, according to Vinfast’s schedule and standards

Related Articles

04.06.2026

THANH TIEN PROJECT

Supply and installation of equipment for modern sheet metal processing lines The number of machines: - Yawei CNC bending machine: 4 - Yawei CNC punching machine: 1 - Grooving machine: 1 - Yawei Laser ...

04.06.2026

DAI DUNG PROJECT

Supply and installation of equipment for steel structure line The number of machines: - Horizontal welding machine: 2 - Welding port: 1 - Yawei HLG 24240 6KW Laser Cutting Machine: 1 (2.4m wide, 24m ...

28.05.2026

SBC PROJECT

Requirements: supply and install steel structure processing equipment line including: fixing machine, welding machine, straightening machine, 15KW laser cutting machine, all equipment is controlled by ...

Notice

1800 1123